Requirements traceability matrix

Requirement to deliverable and back again. The two directions fail differently and both are shown.

Demonstration project - no figure here describes a real facilityChanges are not saved
Why

A requirement counts as traced only when the deliverable answering it can actually be approved. An answer nobody has accepted is not an answer.

Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.

Requirements

9

Traced to an approved deliverable

2

Answered by a draft

6

Answered by nothing

1

Requirement to deliverable
RequirementWhat it requiresSourceAnswered by
REQ-A-014
The hydrostatic test pressure shall be not less than 1.5 times the design pressure of the line under test.
ZRF-CTR-APX-AZRF-HTP-0015Drafted, not approved
REQ-A-021
The Contractor shall submit every deliverable listed in the master document register for Company review before construction.
ZRF-CTR-APX-AZRF-ITP-0003, ZRF-CMP-0007, ZRF-PEP-0001, ZRF-PEP-0001-RATraced
REQ-D-003
An inspection and test plan shall be submitted for each work package, identifying every hold point and witness point.
ZRF-CTR-APX-DZRF-ITP-0008, ZRF-ITP-0003Traced
REQ-D-011
Pressure testing shall be witnessed by the Company representative and the record signed before reinstatement.
ZRF-CTR-APX-DZRF-HTP-0015Drafted, not approved
REQ-S-3300-18
The test medium shall be filtered potable water with a chloride content of not more than 30 ppm.
ZRF-SPC-3300ZRF-HTP-0015Drafted, not approved
REQ-S-3300-22
The test pressure shall be held for not less than 2 hours with no visible leakage and no pressure loss.
ZRF-SPC-3300ZRF-HTP-0015Drafted, not approved
REQ-S-4100-07
Every instrument loop shall be checked from the field element to the control system indication before commissioning.
ZRF-SPC-4100ZRF-LCR-0021Drafted, not approved
REQ-ISO-15649-9
Pressure testing requirements for piping systems. Clause text not reproduced: no licensed copy is held.
ISO 15649 not heldZRF-HTP-0015Drafted, not approved
REQ-SUG-001
Consider recording ambient temperature at the start and end of the hold period, to explain a pressure change that is thermal rather than a leak.
ZRF-SPC-3300nothingUnanswered

Both directions, because they fail differently

Forward finds the requirement nothing answers, which surfaces at handover. Backward finds the deliverable that answers nothing, which usually means somebody wrote a document the contract never asked for.
Drafted is not traced

A requirement answered by a draft with an open blocking comment is not traced. The answer exists and nobody has accepted it, and a matrix that counted it as traced would report compliance that has not been established.

A source the project does not hold

A requirement citing a standard the project holds no copy of is shown with its source marked not held. The requirement is still real - somebody wrote it down - but nobody can check it against the clause it claims to come from.