Schedule and activities
The imported schedule, what each activity is linked to, and how strong that link is.
Why
Percent complete is as the schedule states it. It is never combined with deliverable or verification state: those are different facts about the same work.
Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.
Activities
12
Critical
8
Complete
0
Not started
6
| Activity | Name | Window | As planned | Discipline | Linked to |
|---|---|---|---|---|---|
| A1000 | Detailed design - condensate export | 2026-06-01 to 2026-11-30 | 72%72% | PRO | nothing |
| A1010 | P&ID development | 2026-06-01 to 2026-10-28 | 95%95% | PRO | nothing |
| A1020 | Line list and piping material selection | 2026-07-15 to 2026-10-22 | 88%88% | PIP | ZRF-HTP-0015matched on discipline - a guess, not a traced link |
| A1030 | Equipment datasheets | 2026-08-01 to 2026-11-14 | 64%64% | MEC | nothing |
| A1040 | Instrument index and datasheets | 2026-08-15 to 2026-11-28 | 55%55% | INS | ZRF-LCR-0021matched on discipline - a guess, not a traced link |
| A1050 | Electrical single line diagrams | 2026-09-01 to 2026-12-12 | 40%40% | ELE | ZRF-ETR-0004matched on discipline - a guess, not a traced link |
| A2000 | Construction - condensate export | 2026-12-01 to 2027-06-30 | 0%0% | CON | nothing |
| A2010 | Piping fabrication and installation | 2026-12-01 to 2027-04-30 | 0%0% | PIP | ZRF-HTP-0015matched on discipline - a guess, not a traced link |
| A2020 | Pressure testing and reinstatement | 2027-03-15 to 2027-05-28 | 0%0% | PIP | ZRF-HTP-0015matched on discipline - a guess, not a traced link |
| A3000 | Commissioning - condensate export | 2027-05-01 to 2027-08-31 | 0%0% | COM | ZRF-CMP-0007matched on discipline - a guess, not a traced link |
| A3010 | Loop checking | 2027-05-01 to 2027-06-15 | 0%0% | INS | ZRF-LCR-0021matched on discipline - a guess, not a traced link |
| A4000 | Handover | 2027-09-01 to 2027-09-30 | 0%0% | COM | ZRF-CMP-0007matched on discipline - a guess, not a traced link |
Progress is not combined with anything
The links are weak, and said to be
An activity is matched to deliverables by discipline. That is a guess: an activity named “P&ID development” probably relates to the process deliverables, and nothing in the schedule says so. Presenting it as a traced relationship would be inventing a link the data does not contain.
Test packs
- ZRF-TP-001Not linked to an activity
- ZRF-TP-002Not linked to an activity
No activity names a test pack, so no link exists. Why