ZRF-HTP-0015 validation

Every gate between this deliverable and issue, with what would have to happen for each failure.

Demonstration project - no figure here describes a real facilityChanges are not saved
Why

Each gate is evaluated against the project's own records when the page renders.

Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.

Gates

8

Passed

3

Failed

5

Blocking issue

4

This deliverable cannot be issued

4 gates fail. A validation page that reported a score would let somebody read “eight of ten passed” as nearly ready, when one of the two failures is a safety-critical value two documents disagree about.

Gates

Validation gates
GateOutcomeWhat was foundWhat would fix it
Required inputs presentFailApproved test pressure basis: the design pressure of P-1201A is in conflict between the datasheet and the line listobtain the missing input, or record a deviation
Source documents readablePassevery source document has been read—
Requirements acceptedFail2 not acceptedaccept the requirement, or detach it if it does not apply
No open blocking commentFail5.1: The test pressure basis cites the line list, which states 26 barg, while the datasheet for P-1201A states 24 barg. The derived test pressure cannot be stated until this is resolved.; 9: Acceptance criteria state a 2 hour hold. Appendix D requires the hold to be witnessed; the procedure does not say who witnesses it or what they sign.answer the comment; only the reviewer who raised it may close it
Independent check assignedPasschecked by N. Okonkwo—
Approver is not the authorPassno approver assigned yet—
No safety-critical value in conflictFailP-1201A, PT-1201, HV-3101, 12-CD-1201-150-A1A in conflictdecide which document governs on the reconciliation page
Template conformanceCannot be checkedno client template has been supplied, so conformance cannot be checkedobtain the client's controlled template
A gate nobody can check

Template conformance is reported as not checkable rather than as passing. No client template has been supplied, so there is nothing to conform to - and a gate that passes because the check was skipped is worse than one that fails, because it appears in the record as evidence.