Menu

Company standards

The customer's own specifications and procedures, and where they sit in the precedence hierarchy.

Demonstration project - no figure here describes a real facilityChanges are not saved
Why

Read from the project's own document register. Precedence is shown and never applied automatically.

Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.

Company documents

2

Requirements from them

4

Current revisions

2

Precedence applied automatically

0

Precedence is shown, never applied

The precedence hierarchy as this project states it

Precedence
OrderKindHeld by the projectApplied automatically
1Contract and its appendices3No
2Project and company specifications2No
3International standardscited, not heldNo

Company documents held

Company standards
DocumentTitleClassRevRequirements
ZRF-SPC-3300Piping Material and Pressure Testing SpecificationspecificationC13
ZRF-SPC-4100Instrumentation and Control SpecificationspecificationB1