Project specifications
The specifications this project issued, and the requirements extracted from each.
Why
Requirement counts are the requirements actually extracted from each document, not an estimate of what it contains.
Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.
Specifications
2
Pages held
84
Requirements extracted
4
Text may be reproduced
2
the project wrote them
These the project may quote
ZRF-SPC-3300 Piping Material and Pressure Testing Specification
Revision C1, issued 2026-04-10 for design. 48 pages held.
| Reference | Clause | What it requires | Class | Confidence | |
|---|---|---|---|---|---|
| REQ-S-3300-18 | clause 18.3 | The test medium shall be filtered potable water with a chloride content of not more than 30 ppm. | mandatory | 94%Unverified | Accepted |
| REQ-S-3300-22 | clause 22.1 | The test pressure shall be held for not less than 2 hours with no visible leakage and no pressure loss. | mandatory | 93%Unverified | Accepted |
| REQ-SUG-001 | clause 18 | Consider recording ambient temperature at the start and end of the hold period, to explain a pressure change that is thermal rather than a leak. | informative | 50%Unverified | Not accepted |
3 requirements extracted from 48 pages. Why
ZRF-SPC-4100 Instrumentation and Control Specification
Revision B, issued 2026-04-18 for design. 36 pages held.
| Reference | Clause | What it requires | Class | Confidence | |
|---|---|---|---|---|---|
| REQ-S-4100-07 | clause 7.2 | Every instrument loop shall be checked from the field element to the control system indication before commissioning. | mandatory | 91%Unverified | Accepted |
1 requirement extracted from 36 pages. Why