Project specifications

The specifications this project issued, and the requirements extracted from each.

Demonstration project - no figure here describes a real facilityChanges are not saved
Why

Requirement counts are the requirements actually extracted from each document, not an estimate of what it contains.

Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.

Specifications

2

Pages held

84

Requirements extracted

4

Text may be reproduced

2

the project wrote them

These the project may quote

The project’s own document, so its clauses may be reproduced.

ZRF-SPC-3300 Piping Material and Pressure Testing Specification

Revision C1, issued 2026-04-10 for design. 48 pages held.

Requirements from ZRF-SPC-3300
ReferenceClauseWhat it requiresClassConfidence
REQ-S-3300-18clause 18.3The test medium shall be filtered potable water with a chloride content of not more than 30 ppm.mandatory94%UnverifiedAccepted
REQ-S-3300-22clause 22.1The test pressure shall be held for not less than 2 hours with no visible leakage and no pressure loss.mandatory93%UnverifiedAccepted
REQ-SUG-001clause 18Consider recording ambient temperature at the start and end of the hold period, to explain a pressure change that is thermal rather than a leak.informative50%UnverifiedNot accepted

3 requirements extracted from 48 pages. Why

ZRF-SPC-4100 Instrumentation and Control Specification

Revision B, issued 2026-04-18 for design. 36 pages held.

Requirements from ZRF-SPC-4100
ReferenceClauseWhat it requiresClassConfidence
REQ-S-4100-07clause 7.2Every instrument loop shall be checked from the field element to the control system indication before commissioning.mandatory91%UnverifiedAccepted

1 requirement extracted from 36 pages. Why