Deliverables
Every deliverable on the project, its state, and what stands between it and the next one.
Demonstration project - no figure here describes a real facilityChanges are not saved
Why
Blockers are assembled from the project's gaps, comments and role assignments each time the page renders.
Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.
Deliverables
8
Draft
2
In check or review
3
Approved
1
With an open gap
5
| Number | Title | Discipline | State | What is in the way | |
|---|---|---|---|---|---|
| ZRF-CMP-0007 | Commissioning Procedure - Cooling Water System 31 | COM | in check | open gap: Commissioning sequence: the system boundary for SYS-31-01 is in dispute | Open |
| ZRF-ETR-0004 | Electrical Test Report - Utilities MCC | ELE | draft | open gap: Insulation test basis: the test voltage has not been confirmed | Open |
| ZRF-HTP-0015 | Hydrotest Procedure - Condensate Export System 12 | PIP | in review | open gap: Approved test pressure basis: the design pressure of P-1201A is in conflict between the datasheet and the line list | Open |
| ZRF-ITP-0003 | Inspection and Test Plan - Piping Fabrication | QUA | approved | Nothing | Open |
| ZRF-ITP-0008 | Inspection and Test Plan - Condensate Export Piping Supports | QUA | in review | Ready for the next step | Open |
| ZRF-LCR-0021 | Loop Check Record - PIC-1201 | INS | draft | open gap: Functional test criteria: the control narrative has not been issued | Open |
| ZRF-PEP-0001 | Project Execution Plan | PMG | issued | open gap: Client document numbering requirements: Appendix F has not been received | Open |
| ZRF-PEP-0001-RA | Project Execution Plan | PMG | superseded | Ready for the next step | Open |