Reviewer assignments
Who holds each deliverable, in which discipline, and where the separation of duties is not yet established.
Why
Assignments are checked against the capability the person holds and the discipline they work in.
Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.
Deliverables
8
Fully assigned
5
Missing a checker or reviewer
1
People with a review capability
4
Separation of duties is established here
Assignments
| Deliverable | Discipline | Stage | Author | Checker | Reviewer | Approver | |
|---|---|---|---|---|---|---|---|
| ZRF-LCR-0021 | INS | draft | M. Silva | none | none | none | In discipline |
| ZRF-CMP-0007 | COM | in check | J. Novak | S. Lindqvist | none | none | In discipline |
| ZRF-ETR-0004 | ELE | draft | T. Adeyemi | none | none | none | In discipline |
| ZRF-HTP-0015 | PIP | in review | A. Rahman | N. Okonkwo | S. Lindqvist | none | Reviewer is PRO |
| ZRF-ITP-0003 | QUA | approved | N. Okonkwo | A. Rahman | S. Lindqvist | R. Haddad | Reviewer is PRO |
| ZRF-ITP-0008 | QUA | in review | N. Okonkwo | A. Rahman | S. Lindqvist | R. Haddad | Reviewer is PRO |
| ZRF-PEP-0001 | PMG | issued | K. Mensah | R. Haddad | D. Farouk | R. Haddad | Reviewer is PRO |
| ZRF-PEP-0001-RA | PMG | superseded | K. Mensah | R. Haddad | D. Farouk | R. Haddad | Reviewer is PRO |
Assign somebody
A reviewer from another discipline
Allowed, and flagged. A process engineer reviewing a piping procedure for interface fit is a real and useful thing. It is also how a document gets reviewed by somebody not competent to review it, so the mismatch is shown and a person decides.