ZRF-ETR-0004 validation
Every gate between this deliverable and issue, with what would have to happen for each failure.
Why
Each gate is evaluated against the project's own records when the page renders.
Writes are validated against the engineering rules and then refused, because no database has been configured for this environment.
Gates
8
Passed
3
Failed
5
Blocking issue
4
This deliverable cannot be issued
Gates
| Gate | Outcome | What was found | What would fix it |
|---|---|---|---|
| Required inputs present | Fail | Insulation test basis: the test voltage has not been confirmed | obtain the missing input, or record a deviation |
| Source documents readable | Pass | every source document has been read | — |
| Requirements accepted | Fail | no requirement is attached to this deliverable | accept the requirement, or detach it if it does not apply |
| No open blocking comment | Pass | no blocking comment is open | — |
| Independent check assigned | Fail | no checker has been assigned | assign a checker who is not the author |
| Approver is not the author | Pass | no approver assigned yet | — |
| No safety-critical value in conflict | Fail | P-1201A, PT-1201, HV-3101, 12-CD-1201-150-A1A in conflict | decide which document governs on the reconciliation page |
| Template conformance | Cannot be checked | no client template has been supplied, so conformance cannot be checked | obtain the client's controlled template |
A gate nobody can check
Template conformance is reported as not checkable rather than as passing. No client template has been supplied, so there is nothing to conform to - and a gate that passes because the check was skipped is worse than one that fails, because it appears in the record as evidence.